Skip to main content

PMS 448

Chaps – Protective, Summer Weight 36" Long

NFES #
000078
Category
Cordura
Updated
Storage and Shelf Life Checks
None

Initial Inspection/Disposal Criteria

  1. Inspect fabric and webbing for any holes, cuts, tears, or burns. Tears less than ½ inch can be repaired.  Tears or cuts longer than ½” render the item unserviceable. 
  2. Inspect for any area of abrasion that has weakened fabric beyond repair.
  3. Inspect for any webbing that is cut, burned, or abraded beyond economical repair.
  4. Inspect each leg. If either leg has more than five patches, remove from service.
  5. Chaps should be removed from service if not labeled with specification USFS 6170-4F, 4G, or 4H or are not certified to NFPA 1977‑05.
  6. Inspect all molded nylon hardware for dirt, cracks, breaks, and proper function.
  7. Return to stock if item does not show any signs of use and passes visual inspection.
  8. Refurbish if the item needs to be cleaned and/or damage can be repaired economically.
  9. Dispose of item if it fails initial inspection.
  10. Dispose of item if wood chips and sawdust are evident inside the layers at the bottom of the chaps.
  11. Dispose of item if the first layer of yellow Kevlar has a cut that is more than 1 inch long.
  12. Dispose of item if improper repairs have been made, such as patch jobs that stitched through the Kevlar.

Refurbishing Procedures

A. Cleaning

  1. Allow any mud or loose dirt to dry and then remove using a stiff-bristle brush.  If stains remain, wash as recommended below.
  2. Remove light oil and dirt stains by brushing with a Citrosqueeze® solution, brush with a bristle brush, rinse thoroughly and hang to dry.
  3. For heavier oil or grease soak in a Citrosqueeze® solution for at least 4 hours, brush with a bristle brush, rinse thoroughly and hang to dry.

DO NOT MACHINE WASH OR DRY.

DO NOT USE BLEACH TO CLEAN FABRIC.

DO NOT PRESSURE WASH.

B. Repair

  1. Repair burn holes and cuts. 
  2. Use Seam Grip® to repair holes or cuts in the nylon shell. 
  3. To repair holes less than ½ inch in length, apply a dot of Seam Grip® over the hole and allow the Seam Grip® to dry. 
  4. Allow chaps to dry for at least 12 hours before using.
  5. Replace burned, abraded, or cut nylon webbing with like items.
  6. Replace broken or nonfunctioning hardware.

C. Testing for Performance

  • Retest all replaced hardware. The hardware should function easily with little force being applied and no difficulty in the release.

D. Repackaging

  • Pack 10 each in NFES #002007 carton (24” x 16” x 16”).

NWCG Latest Announcements

NEW! NWCG Wildland Urban Interface Mitigation Field Guide, PMS 053

Date: March 12, 2025
Contact: Wildland Urban Interface Mitigation Committee

The NWCG Wildland Urban Interface Mitigation Field Guide, PMS 053 provides mitigation practitioners at all experience levels with recommendations on the most effective and efficient ways to accomplish mitigation work in communities at risk to wildfire damage or destruction. The content in this guide was written in coordination with the NWCG Standards for Mitigation in the Wildland Urban Interface, PMS 052.

References:

NWCG Wildland Urban Interface Mitigation Field Guide, PMS 053 

Updated, NWCG Standards for Wildland Fire Module Operations, PMS 430

Date: March 11, 2025
Contact: Fire Use Subcommittee
Wildland Fire Module Unit

The NWCG Standards for Wildland Fire Module Operations, PMS 430 standardizes procedures and expectations for Wildland Fire Modules (WFMs). These standards are to be used by staff, supervisors, specialists, and technicians for planning, administering, and conducting WFM operations. These standards will also be used as a measure of WFM qualifications, capabilities, and expected performance, for both Type 1 and Type 2 WFMs.

References:

NWCG Standards for Wildland Fire Module Operations, PMS 430

NEW! NWCG Standards for Airtanker Operations, PMS 514

Date: March 7, 2025
Contact: National Interagency Aviation Committee

The NWCG Standards for Airtanker Operations, PMS 514 establishes the standards for dispatching, utilizing, and coordinating airtankers on interagency wildland fires. These standards should be used in conjunction with the NWCG Standards for Aerial Supervision (SAS), PMS 505, NWCG Standards for Airtanker Base Operations (SABO), PMS 508, and any applicable agency plans.

References:

NWCG Standards for Airtanker Operations, PMS 514

Incident Position Standards and Next Gen Position Task Books Now Available for Dispatch Incident Positions

Date: March 5, 2025
Contact: National Coordination System Committee

NWCG is excited to announce that Incident Position Standards and Next Generation Position Task Books are now available for all six Dispatch positions:

  • Aircraft Dispatcher
  • Expanded Dispatch Coordinator
  • Expanded Dispatch Recorder
  • Expanded Dispatch Supervisory Dispatcher
  • Expanded Dispatch Support Dispatcher
  • Initial Attack Dispatcher

The Performance Support Packages for these positions, including the Expanded Dispatch Job Aid, J-601 and the Initial Attack and Aircraft Dispatcher Job Aid, J-602, were developed as part of the Incident Performance and Training Modernization (IPTM) effort. These resources support trainees, qualified personnel, and evaluators in their roles.

Any changes to qualification pathways will take effect with the next update of the NWCG Standards for Wildland Fire Position Qualifications, PMS 310-1.

References:

NWCG Aircraft Dispatcher Position Page 

NWCG Expanded Dispatch Coordinator Position Page 

NWCG Expanded Dispatch Recorder Position Page 

NWCG Expanded Dispatch Supervisory Dispatcher Position Page 

NWCG Expanded Dispatch Support Dispatcher Position Page 

NWCG Initial Attack Dispatcher Position Page 

NWCG Job Aids