Skip to main content

Pump – Barrel, For 55 GL Drum

NFES #
000149
Category
Fuel Handling
Updated
Storage and Shelf Life Checks
None

Hand crank, barrel pump.Initial Inspection/Disposal Criteria

  1. Check for fuel in hose and pipe. Dispose of fuel if present.
  2. Check hose and suction pipe for obstructions and remove if possible.
  3. Check discharge hose for cracking and signs of wear. Replace as needed.
  4. Inspect for missing parts and obvious damage to stem pipe, hose, or housing.
  5. Check bolts and plugs in pump head to make sure they are tight. Check seals for signs of leaks. Inspect stem pipe and hose for thread damage. Remove or replace as needed.
  6. Return to stock if clean and in unused condition.
  7. Rotate handle to make sure that gears move freely. Dispose of pump if froze up.
  8. Test and refurbish item if it passes visual inspections.

Refurbishment Procedures

A. Testing for Performance

  1. Install drop stem pipe and discharge hose on to pump head and ensure that the threads are not damaged. If replacement parts are needed, use only manufacturer specific parts. Not all components are interchangeable.
  2. If available, install pump into barrel of fuel and pump from one barrel to another. Follow all safety regulations including wearing PPE. Ensure both barrels / containers are on a berm and are labeled with all proper hazmat labels. Consult with local safety personnel for guidance. Make sure pump does not leak, operates correctly, and has drained completely before removing from barrel.
  3. If barrels of fuel are not available, secure plastic bag to the end of the drop stem and secure with rubber band (see photo below). Turn the hand pump and watch the plastic bag to see if the pump sucks the air out of the bag. This will ensure suction is working. Spray pump head and connections with soapy water and check seals for leaks.
    • While cranking the hand pump, you should feel some resistance, but it should crank smoothly. Any catches during the operation could mean damage internally.
  4. Do not pump water through the system. This will freeze up the internal gears.

B. Repair

  1. Internal repairs to the pump are not recommended at this time.
  2. Replacement parts should be manufacturer specific. Interchanging parts could result in leaks and operational failure.

C. Cleaning

  1. Wipe pump head off with degreaser and rag. Do not submerge in water or allow water into pump head.
  2. Stem pipe and discharge hose can be cleaned separately from the pump head. Use degreaser and hose or pressure wash.
  3. Allow to air dry completely.

D. Repackaging

  1. Remove stem pipe, discharge hose, and handle from pump head.
    • Recommend 1 each in an NFES #000385 carton. (7 ¼” X 9 ¼” X 26”)

 

Stem pipe with plastic bag around the end.

 

 

 

NWCG Latest Announcements

Updated, NWCG Standards for Wildland Fire Module Operations, PMS 430

Date: March 11, 2025
Contact: Fire Use Subcommittee
Wildland Fire Module Unit

The NWCG Standards for Wildland Fire Module Operations, PMS 430 standardizes procedures and expectations for Wildland Fire Modules (WFMs). These standards are to be used by staff, supervisors, specialists, and technicians for planning, administering, and conducting WFM operations. These standards will also be used as a measure of WFM qualifications, capabilities, and expected performance, for both Type 1 and Type 2 WFMs.

References:

NWCG Standards for Wildland Fire Module Operations, PMS 430

NEW! NWCG Standards for Airtanker Operations, PMS 514

Date: March 7, 2025
Contact: National Interagency Aviation Committee

The NWCG Standards for Airtanker Operations, PMS 514 establishes the standards for dispatching, utilizing, and coordinating airtankers on interagency wildland fires. These standards should be used in conjunction with the NWCG Standards for Aerial Supervision (SAS), PMS 505, NWCG Standards for Airtanker Base Operations (SABO), PMS 508, and any applicable agency plans.

References:

NWCG Standards for Airtanker Operations, PMS 514

Incident Position Standards and Next Gen Position Task Books Now Available for Dispatch Incident Positions

Date: March 5, 2025
Contact: National Coordination System Committee

NWCG is excited to announce that Incident Position Standards and Next Generation Position Task Books are now available for all six Dispatch positions:

  • Aircraft Dispatcher
  • Expanded Dispatch Coordinator
  • Expanded Dispatch Recorder
  • Expanded Dispatch Supervisory Dispatcher
  • Expanded Dispatch Support Dispatcher
  • Initial Attack Dispatcher

The Performance Support Packages for these positions, including the Expanded Dispatch Job Aid, J-601 and the Initial Attack and Aircraft Dispatcher Job Aid, J-602, were developed as part of the Incident Performance and Training Modernization (IPTM) effort. These resources support trainees, qualified personnel, and evaluators in their roles.

Any changes to qualification pathways will take effect with the next update of the NWCG Standards for Wildland Fire Position Qualifications, PMS 310-1.

References:

NWCG Aircraft Dispatcher Position Page 

NWCG Expanded Dispatch Coordinator Position Page 

NWCG Expanded Dispatch Recorder Position Page 

NWCG Expanded Dispatch Supervisory Dispatcher Position Page 

NWCG Expanded Dispatch Support Dispatcher Position Page 

NWCG Initial Attack Dispatcher Position Page 

NWCG Job Aids 

Incident Position Standards and the Next Generation Position Task Books Now Available for DMOB, DOCL, and RESL

Date: February 28, 2025
Contact: Incident Operations Subcommittee

NWCG is excited to announce that Incident Position Standards and the Next Generation Position Task Books are now available for Demobilization Unit Leader (DMOB), Documentation Unit Leader (DOCL), and Resources Unit Leader (RESL).

The Performance Support Packages for these positions, including a job aid for RESL, were developed as part of the Incident Performance and Training Modernization (IPTM) effort. These resources support trainees, qualified personnel, and evaluators in their respective roles.

Any changes to qualification pathways will take effect with the next update of the NWCG Standards for Wildland Fire Position Qualifications, PMS 310-1.

References:

NWCG Demobilization Unit Leader Position Page 

NWCG Documentation Unit Leader Position Page 

NWCG Resources Unit Leader Position Page