Incident Summary:

On July 2, 1994, seven miles west of Glenwood Springs, Colo., lightning ignites a fire in piñon-pine and juniper on a ridge at the base of Storm King Mountain. The entire general area, in a one-year drought, is experiencing low humidities and record-high temperatures. Over the next two days, the South Canyon Fire increases in size. Initial attack resources are assigned. Four days later, on July 6, a dry cold front moves into the fire area. As winds and fire activity increases, the fire makes several rapid runs. Fourteen firefighters perish as they try to outrun the flames.


South Canyon incident map

July 5 – Summary of Activities:

Red flag warnings and very high to extreme fire danger are predicted again today.

A crew of seven firefighters hikes up into the South Canyon Fire at the base of Storm King Mountain. They cut Helispot 1 and begin direct fireline construction downhill along the fire’s edge below this helispot.

The IC orders another district engine crew, one helicopter, and one 20-person hand crew. A load of eight smokejumpers is then substituted for the hand crew.

To support fireline construction, an air tanker retardant drop is requested. After the first load is dropped, due to steep terrain and gusty winds, the IC and pilot agree that more drops would be ineffective.

At 5:30 p.m. the IC and engine crew leave the fire to refurbish equipment. Fifteen minutes later, 8 smokejumpers are dropped at the top of the fire. The IC directs them to work on the fireline from the helispot downhill toward the west drainage.

The Jumper-in-Charge informs the IC that the fire has crossed their fireline and is burning actively. The jumpers begin building fireline on the east side of the ridge.  After sizing-up the current fire, the Jumper-in-Charge orders two Type 1 hand crews. By 10 p.m., the fire has grown 20 acres today. It now covers 50 acres.

Discussion Points:

Downhill fireline construction is hazardous in steep terrain, fast-burning fuels, and rapidly changing weather. Downhill fireline construction should not be attempted unless there is no tactical alternative.

If your fire crew was assigned to construct fireline downhill on Storm King, what would your concerns be? Could you perform this operation safely? (Reference page 1, 6 and 8 in your IRPG for this discussion.)

 

Last Modified / Reviewed:

Have an idea or feedback?

Share it with the NWCG 6MFS Subcommittee.


Follow NWCG on Twitter and Facebook

NWCG Latest Announcements

2025 Professional Reading Program

Date: February 18, 2025
Contact: Wildland Fire Leadership Development Program (WFLDP)

The Wildland Fire Leadership Development Program is announcing the 2025 Professional Reading list! The goal of the annual reading list is to promote the reading and discussion of the books throughout the year.

The five books chosen for this year are: Surf When You Can by Brett Crozier, Man’s Search for Meaning by Viktor E. Frankl, Elephant Company by Vicki Constantine Croke, Simply Managing by Henry Mintzberg, and Chop Wood Carry Water by Joshua Metcalf.

References:

Professional Reading Program

Task Group Volunteers Needed to Update the Property Loss or Damage Report, OF 289

Date: February 5, 2025
Contact: Julie Bennett, Incident Business Committee Chair

The Incident Business Committee (IBC) is requesting volunteers for a new task group to revise the 1981 version of the Property Loss or Damage Report, OF 289 and create an incident replacement job aid. The volunteers may be recruited from within or outside the Geographic Area Incident Business Committees.

References:

IBC Memorandum 25-02

IBC Correspondence

2025 Updates to the NWCG Standards for Wildland Fire Position Qualifications, PMS 310-1

Date: February 4, 2025
Contact: Incident and Position Standards Committee

The NWCG Incident and Position Standards Committee has updated the NWCG Standards for Wildland Fire Position Qualifications, PMS 310-1. 

These updates address changes to incident position names and requirements for qualification, training, and experience. Updates related to the implementation of Complex Incident Management (CIM) are also included.  

The NWCG Wildland Fire Position Qualification Flowchart, PMS 308 has also been updated to reflect the recent changes.

References:

NWCG Standards for Wildland Fire Position Qualifications, PMS 310-1

NWCG Wildland Fire Position Qualification Flowchart, PMS 308

NWCG Memo: 2025-01 January 2025 Updates to the NWCG Standards for Wildland Fire Positions Qualifications, PMS 310-1

NWCG Equipment Technology Committee Releases Safety Warning: 25-001 Non-specification fire shelters

Date: January 15, 2025
Contact: Equipment Technology Committee

The Equipment Technology Committee (ETC) has released Safety Warning: 25-001 Non-specification fire shelters. Non-specification fire shelters claiming to meet Forest Service (FS) fire shelter specification 5100-606 were first found in February of 2023. As of September 2024, non-specification shelters are again being advertised and sold on the open market.

This Safety Warning outlines details and recommended procedures to purchase FS specification shelters made with materials and components that meet performance criteria and toxicity testing requirements outlined in FS Specification 5100-606. 

For additional information on identifying non-specification shelters, please view ETC Safety Warning 23-01.

References:

ETC Safety Warning 25-001: Non-specification fire shelters

NWCG Equipment Technology Committee

ETC Safety Warning 23-01