Incident Summary:

The Angeles National Forest in Southern California is known for its steep, rocky terrain and common strong, dry downhill wind, known as Santa Ana winds. At 0519, a fire was started by a faulty electric line at the Nike Missile Site on an exposed ridge at the head of Loop Canyon. Chamise, sage, and sumac were the dominant fuels, with critically low live fuel moistures. Santa Ana conditions prevailed, and the fire was driven downhill rapidly by 60 mph northeast winds toward an urban area at the bottom of the canyon. The temperature was 73 °F with 15% relative humidity (RH). At 0520, a lookout reported the fire. At 0536, initial attack takes place. At 0600, more crews arrive. The Fire Weather Forecaster issued a warning at 0830 of Santa Ana conditions in the fire area, with a high temperature of 95 °F and 10% RH. Firefighters were experiencing east-northeast winds at 40 to 60 mph. At 1300, the temperature was 80 °F with 12% RH.

 

The El Cariso Hotshots arrive at Contractors Point above Loop Canyon at 1430. They receive instruction to leapfrog the other crews and cold trail down the east flank. Much of the fire’s edge was in or near a chimney canyon. Winds were decreasing but with continued considerable channeling and eddies. At 1500, the El Cariso crew decided it was possible to cold trail down the chimney and tie in with the crews working the lower edge of the fire. It was noted that there was no clean black. Only 500 feet away from tying in with cat lines at the bottom at 1535, the terrain was too steep. They decided to go indirect 50 to 100 feet away from the fire’s edge. They were working in an area of unburned fuel and hazardous topography and were unaware that the fire had established a hot spot at the base of the chimney below them, burning in sumac bushes and heavy litter.Their escape routes were inadequate. At 1545, flare-up occurs and a “reverse tool order” (turn back and get out fast) was immediately given to the crew.

 

In less than 1 minute the fire flashes through the 2,200-foot chimney, overcoming the 23 firefighters.


Discussion Points:

The Fire Record 1966 shield graphic showing flames,and thunderbolt in front of mountains and timber.In 1966, this incident made us recognize the need for downhill line construction guidelines.

The El Cariso crew was not notified that the assignment had previously been turned down.

  • Review How to Properly Refuse Risk in the IRPG (gray section). Identify what must be communicated and to whom if an assignment is turned down.

Crews working at the bottom of the fire saw that the fire had moved below El Cariso crew in the chimney. Unfortunately, the crew leaders could not communicate a warning to El Cariso since it was not common for crew leaders to carry or be issued radios as we do today.

  • Identify the protocol your crew/unit has in place to inform others of hazards.

When the flare up occurred, 11 crew members moved into and near an emergency survival area. Personal protective equipment (PPE) and fire shelters would have lessened the severity of their injuries.

  • Ensure your crew has the appropriate PPE, that it is in good condition, and they know how to wear/use it correctly.

Many firefighters across the country will fight fire in Southern California at some point in their careers.

  • What unique topographic, weather, and fuel conditions require you to be watchful?

Special thanks to Rich Leak, Ed Cosgrove, and the El Cariso Hotshots for sharing their stories and history.

 

 

Have an idea or feedback?

Share it with the NWCG 6MFS Subcommittee.


Follow NWCG on Twitter and Facebook

NWCG Latest Announcements

2024 Week of Remembrance

Date: June 27, 2024
Contact: 6 Minutes for Safety Subcommittee 

As we approach the 2024 Week of Remembrance (WOR), June 30 to July 6, we dedicate this time to thoughtfully reviewing and recognizing the events of the 2018 Mendocino Complex. As such, this year’s theme of “Learning From the Mendocino Complex” embodies a longstanding hallmark of WOR, honoring through learning.

Throughout the week, our energy will be directed toward fostering generative conversations in briefing rooms and at tailgates.

References:

6 Minutes for Safety - 2024 Week of Remembrance

Wildland Fire Lessons Learned Center

Updated NWCG Wildland Fire Risk and Complexity Assessment, PMS 236

Date: June 24, 2024
Contact: Incident and Position Standards Committee 

The June 2024 update of the NWCG Wildland Fire Risk and Complexity Assessment, PMS 236, is now available to meet the current needs for incident management typing.

The NWCG Wildland Fire Risk and Complexity Assessment should be used to evaluate firefighter safety issues, assess risk, and identify the appropriate incident management organization based on incident complexity. Assessing risk, determining incident complexity, and identifying an appropriate incident management organization is a subjective process based on examining a combination of indicators or factors, which can change over time.

References:

NWCG Wildland Fire Risk and Complexity Assessment, PMS 236

Operations Branch Director (OPBD) Next Gen PTB Available

Date: June 10, 2024
Contact: NWCG Feedback 

The NWCG Position Task Book for Operations Branch Director (OPBD), PMS 311-109 is now available for use within the OPBD position qualification pathway. As part of the transition to Complex Incident Management (CIM), the OPBD Next Gen PTB was developed and the position qualification pathway updated.

More information about the Next Gen PTB format can be found on the NWCG Position Task Book webpage.

References:

Operations Branch Director Position Page

Operations Branch Director Next Gen PTB

NWCG Position Task Books

Updated NWCG Standards for Interagency Incident Business Management, PMS 902

Date: June 5, 2024
Contact: NWCG Incident Business Committee 

The 2024 revision of the NWCG Standards for Interagency Incident Business Management, PMS 902 is now available. The uniform application of interagency incident business management standards is critical to interagency fire operations. PMS 902 assists NWCG agencies in constructively working together to provide effective execution of each agency's incident business management program.