PMS 448

Leadline – 12’, 3000 lb. Capacity

NFES #
000528
Category
Aviation
Updated
Storage and Shelf Life Checks
None

Initial Inspection/Disposal Criteria

  1. Inspect eye and swage for red paint and slippage:
    1. Inspect swage and wire rope eyes for slippage. If slippage has occurred, see Figures 1 and 2, dispose of the leadline.
    2. Visually inspect each swage and eye for red paint, if the paint shows that slippage has not occurred, but the paint is worn in such a way that this determination was difficult, the swage shall be repainted. If paint is not present, send to certified rigging specialist for evaluation.
Figure 1. Painted swage painted-swage-slippage-000380.jpg
Figure 1. Painted Swage Figure 2. Paint showing slippage

 

  1. Inspect for wire rope damage.  If any damage is found then dispose of the wire rope.
    1. Visually inspect length of wire rope for structural damage
  • Kinks in wire rope, see Figure 3.
  • Ballooning of wire rope, see Figure 4.
  • Cut or damaged plastic coating of cable (NFES #000528 only), see Figure 5.
  • Severe Corrosion
  • Abrasion, wear over 1/3 the outer wire diameter, see Figure 6.
  • Reduction in diameter of wire rope.

 

image of a kinked cable image of a cable ballooning
Figure 3. Kink Figure 4. Ballooning
image of a damaged plastic coated wire rope image showing abrasion on a cable
Figure 5. Damaged plastic coated wire rope. Figure 6. Abrasion

 

  1. 6000 pound leadline (NFES #000380)--inspect length of wire rope for damage.
  • Wear heavy protective gloves. Never use an ungloved hand to check the length of the cable.
  • Run a dry rag over the entire length of the wire rope.
  • Flex wire rope to expose breaks. Snags indicate broken wires in the wire rope. If individual broken wires are found, they may be trimmed back. If 4 or more broken wires are found grouped together, then dispose of wire rope.
  1. 3000 pound leadline (NFES #000528)--inspect plastic coated wire rope for damage. Abrasion to plastic coating down to the wire rope may cause corrosion.
  • Run gloved hand over length of plastic coated wire rope to check for any abnormalities such as lumps, depressions, and exposed wire. If plastic coated wire rope has severe damage or corrosion, dispose of properly.  See Figure 5.

 

  1. Measure wire rope diameter and length-
    1. Check wire rope length.
  • Length is measured from center of each thimble. If wire rope length exceeds tolerance, dispose of properly. Note: A hook replacement process was performed where old style spring gate hooks were replaced with self-closing gate hooks, see References. In this retrofit process the leadline length was shortened. The minimum length of the leadline was set at 10 ft. 2 inches. Further as part of the retrofit, the ID tag was to include “Retrofit Leadline.” Therefore short 3,000 lb. rated leadlines are only acceptable if they include the Retrofit Leadline designation on their ID tags, others are to be removed from service.

 

Table 1. Wire Rope Length
Length Tolerance per FSS 5100-503/505
12 feet +/-3 inches
25 feet +/-3 inches
50 feet +/-3 inches

 

Table 2. Wire Rope Diameter

Size Dimension
3000 lbs. 5/16 inch to 5/8 inch
6000 lbs. 1/2 inch to 9/16 inch

 

  1. Check for identification.
    1. Visually inspect leadline for permanently attached tag. Proof load tag shall be permanently attached with a swaged stainless steel wire rope.
    2. Temporary attachments are not allowed, such as wire ties.
    3. Tag shall contain at a minimum the following information: Manufacture Name, Test Company or Trademark; Working Load Limit; and Date of Proof Test (i.e., 06/06 for June, 2006). Note: Older leadlines will have Safe Working Load vice Working Load Limit, both terms are currently acceptable.
    4. If permanently attached proof load tag is not present, missing required information, not made of metal or secured with a non-permanent attachment device (e.g. Ty-Rap zip ties), remove the leadline from service.
  2. Inspect thimble for cracks, wear, and deformation.
    1. Physically examine each thimble for movement by forceful motion with hand.
    2. Thimble may move but should not be loose within the eyelet.
    3. Thimble shall have a smooth arc (see Figure 7.) If thimbles have any cracks, wear, deformation or are loose (see Figure 8.), dispose of leadline.
image of a thimble pear link image of a deformed thimble hook
Figure 7. Thimble, Pear Link and Proof Load Tag Figure 8. Deformed Thimble and Hook
  1. Inspect hook for damage, wear, and deformation.
    1. Check hook for damage such as cracks, nicks, wear, gouges, and deformation, see Figures 9 and 10.
    2. Ensure that hook is not bent or distorted and complies with hook dimensions, see Table 3 and Figure 9.
    3. Ensure hook has a safety latch or has been retrofit with self-locking safety gate that operates correctly.
  • Ensure safety gate opens and closes completely.
  • Examine gate for damage or distortion.
  • Examine gate lock for rounded edge, see Figure 10.
  • Ensure lock latch pin is secure and flush with latch, see Figure 10.
  1. Check hook dimensions, see Table 3 and Figure 9.
  2. If hook is damaged, missing hardware, is distorted, or does not meet dimension requirements, remove leadline from service.
Table 3. Hook Dimensions
Leadline Capacity Style H (max) J (min)
3000 lbs. Self-locking hook 1.0 inch 1.33 inches
6000 lbs. Self-locking hook 1.33 inches 1.7 inches
image of a self locking hook
Figure 9. Dimensions for Hooks
image of a gate lock latch
Figure 10. Examine Gate Lock Latch for rounding.

 

  1. Inspect Ring or Link
    1. Check for damage such as cracks, nicks, wear, and gouges.
    2. Check dimensions for deformations, see Table 4 and Figure 11.
    3. If ring or link is damaged, remove from service.

 

Table 4. Leadline Ring and Pear Link Dimensions
Leadline A B C
3000 lb Leadline 5/8 inch max 1.5 - 3 inch 3 - 4 inch
6000 lb Leadline 0.63 inch max 1.5 - 3 inch 3 - 4.5 inch

 

image showing the dimensions of a pear link and an oval link
Figure 11. Dimension for Pear Link and Oblong Link.

 

  1. Return to stock if leadline is in a sealed carton, or is an open container, but is clean, in unused condition, and passes inspection.
  2. Refurbish if leadline only requires cleaning or has deficiencies identified during inspection that are economically feasible to complete.
  3. Dispose of leadline if it fails inspection and repairs are not practical or economically feasible.

 

 

Refurbishing Procedures

A. Cleaning

  • The cable and hook assembly may be cleaned with hot water only, no soap.

B. Repair

  1. Apply slippage paint to the swage and thimble as shown in Figure 12.
  • The paint shall be a red spray epoxy or acrylic.
  • Mask or cover the area to achieve a painted area similar to Figure 12.
  •  Spray around the swage and do not attempt to spray paint into the ends of swage.
  1. If the Proof Load Tag is missing, the leadline must be sent to a rigging company to be tested per Testing for Performance, as long as the item passed all other inspections.
  2. Upon successful test, the rigging company shall apply a Proof Load Tag that meets/includes the following:
  • Working Load Limit in lbs. • date of proof test (month and year)
  • Name or trademark of the rigging company
  • Text size shall be 0.12 inches in height
  • Tag shall either be stainless steel or brass
  • Tag shall be secured to the leadline with a metal device, e.g., ‘hog ring’, wire cable

 

image of a swage junction showing the paint not disrupted
Figure 12. Swage Paint.

 

C. Testing for Performance

  1. Proof tests must be performed by a certified rigging company when the tag is missing and the leadline is otherwise acceptable and it’s economically feasible to retest the leadline.
  2. The proof test shall apply a load to the item at twice the rated safe working load.
  3. Any certified rigging company can test proof test the leadline assembly.

D. Repackaging

NFES #000528 package 5 each in NFES #008018 carton (12” x 12” x 6”).
NFES #000380 suggested package of 1 each in NFES #008018 carton (12” x 12” x 6”).

 

NWCG Latest Announcements

Updated NWCG Standards for Course Delivery, PMS 901-1 and NWCG Training Course Completion Certificate, PMS 921-1

Date: July 17, 2024
Contact: Training Delivery Committee 

The Training Delivery Committee (TDC) has updated the NWCG Standards for Course Delivery, PMS 901-1 to reflect changes in the standards for course management and delivery. These changes have been reviewed and approved by the members of TDC over the past year. Significant updates include additional delivery methods, updated definitions, and instructions for the use of digital signatures on training certificates. The NWCG Training Course Completion Certificate, PMS 921-1 has been updated to lock after an electronic signature has been applied.

References:

NWCG Standards for Course Delivery, PMS 901-1

NWCG Training Course Completion Certificate, PMS 921-1

IBC Memo 24-01: OF 297 Signature Order and 2024 Fire Season Use IBC Memo 24-02: Summary of Changes for SIIBM, PMS 902

Date: July 15, 2024
Contact: Incident Business Committee 

The NWCG Incident Business Committee (IBC) has recently released two memorandums. The first provides direction on the use of the Emergency Equipment Shift Ticket, OF 297 for the 2024 fire season. Due to delays in hard copy printing, both the 2024 revision and the older version of the Emergency Equipment Shift Ticket, OF 297 are acceptable for use during the 2024 fire season.

The second memorandum documents the updates of the newly revised NWCG Standards for Interagency Incident Business Management (SIIBM), PMS 902. The summary of changes attached to the memo covers the major updates and process changes from the 2022 version.

References:

IBC Memorandum 24-01: OF 297 Signature Order and 2024 Fire Season Use

IBC Memorandum 24-02: Summary of Changes for the NWCG Standards of Interagency Incident Business Management, PMS 902

IBC Memorandum 24-02 Attachment: Summary of Changes

NWCG Standards for Rapid Extraction Module Support, PMS 552

Date: July 10, 2024
Contact: Incident Medical Unit Subcommittee 

A new publication from the Incident Medical Unit Subcommittee is now available. The NWCG Standards for Rapid Extraction Module Support, PMS 552 will be used as a guide and as an opportunity to begin to build out Rapid Extraction Module Support (REMS) modules for the remainder of Fire Year 2024. These standards will be fully implemented as the minimum standard starting in January 2025.

NWCG Standards for Rapid Extraction Module Support outlines the roles, duties, qualifications, and equipment pertinent to REMS. A REMS team, strategically stationed at wildland fires, plays a pivotal role in prioritizing swift access and medical treatment to injured or ill firefighters for safe and efficient egress off the fireline. This ensures their rapid transport to definitive medical care in cases of emergency during firefighting operations, highlighting the invaluable contribution of the REMS team to firefighter safety and well-being.

References:

NWCG Standards for Rapid Extraction Module Support, PMS 552

National Wildland Firefighter Day

Date: July 2, 2024
Contact: National Interagency Fire Center 

The National Wildfire Coordinating Group (NWCG) would like to recognize July 2, 2024, as National Wildland Firefighter Day (NWFFD). Established in 2022, NWFFD honors the dedication of wildland firefighters and support personnel. This day falls within the 2024 Week of Remembrance (June 30 - July 6), providing an opportunity to renew our commitment to wildland firefighter safety while remembering those who have fallen in the line of duty.

NWCG continues to provide leadership to enable interoperable wildland fire operations among federal, state, local, Tribal, and territorial partners. NWCG standards and training establish common practices to contribute to safe, effective, and coordinated national interagency wildland fire operations.

References:

NWCG.gov

Week of Remembrance

National Wildland Firefighter Day