Skip to main content

PMS 448

Chest – Ice 48 QT.

NFES #
000557
Category
Camp
Updated
Storage and Shelf Life Checks
None

Initial Inspection/Disposal Criteria

  1. Visually inspect for damage, cracks, broken, melted parts or evidence of leakage, if any dispose of. 
  2. Inspect lid for proper closure and working hinges. 
  3. Inspect handles. 
  4. Inspect drain plug for leakage or any damage.  
  5. Refurbish if damage is determined to be repairable. 
  6. Return to stock if item is clean, undamaged and/or in unused condition. 
  7. Dispose of item if damage is determined to be unrepairable or if stains cannot be cleaned. 
  8. Salvage any usable parts for future repairs.

Refurbishing Procedures

A. Cleaning

  1. Use pressure washer to clean inside and outside of ice chest. Disinfect per Cache direction. 
  2. If necessary clean stains with a scrubbing pad and mild detergent. 
  3. Rinse thoroughly. 
  4. Stand upside down to air dry and/or wipe down completely to dry.

B. Repair

  1. Lid – replace hinges if possible
  2. Handles –replace if possible
  3. Drain plug– replace if possible
  4. Spray paint top lid of ice chest if any unwanted writing is present
  5. If ice chest has water inside the lid drill a 1/8” hole in lid to take out excess water, use glue from a hot glue gun to fill the hole after completely drained and dry.

C. Testing for Performance

  • If drain plug was replaced, add water to inside of ice chest to ensure drain is not leaking.

D. Repackaging

  1. Stencil and spray paint or use permanent marker to apply NFES #000557 to the exterior of the chest.
  2. Band clean/dry ice chest with one band.
  3. Palletize per local cache option.

 

NWCG Latest Announcements

New Job Aids Available: Packing Lists for Wildland Fire Fireline Personnel and Support Staff, J-101 and J-102

Date: December 3, 2024
Contact: NWCG TRAINING

Two new job aids are now available: Packing List for Wildland Fire Fireline Personnel, J-101 and Packing List for Wildland Fire Support Personnel, J-102, should serve as a baseline for items needed on a wildland fire assignment. These lists will help personnel prepare for a 14 to 21-day assignment on the fireline or in a support role.

References:

Job Aid Catalog

NWCG Packing List for Wildland Fire Fireline Personnel, J-101

NWCG Packing List for Wildland Fire Support Staff, J-102

NWCG Equipment Technology Committee Releases Safety Warning: 24-001 Stihl Chainsaw Toolless Fuel Cap Spill Prevention

Date: November 14, 2024
Contact: Equipment Technology Committee

The Equipment Technology Committee (ETC) has released Safety Warning: 24-001 Stihl Chainsaw Toolless Fuel Cap Spill Prevention. Misaligned toolless fuel caps on Stihl chainsaws have led to recurring fuel spillage, fuel ignition, and burn injuries during wildland fire management operations.

This Safety Warning is intended to highlight the details and recommended procedures for the installation of a Stihl chainsaw toolless fuel cap, as well as how to identify and correct a misaligned, damaged, or broken fuel cap to help prevent fuel spillage.

References:

NWCG Safety Warning: 24-001 Stihl Chainsaw Toolless Fuel Cap Spill Prevention

Advertencia de equipos 24-001: Prevención de derrames de la tapa de combustible sin herramientas de la motosierra Stihl

NWCG Alerts

The Incident Position Standards and Next Generation Position Task Book are now available for Equipment Time Recorder (EQTR)

Date: November 13, 2024
Contact: Incident Business Committee

NWCG is excited to announce that the NWCG Incident Position Standards for Equipment Time Recorder, PMS 350-51 and NWCG Position Task Book for Equipment Time Recorder (EQTR), PMS 311-51 are now available.

The Performance Support Package, which for EQTR, includes the Incident Position Standards and Next Generation Position Task Book were developed through the Incident Performance and Training Modernization (IPTM) effort. The Performance Support Package will support trainees, those qualified in the position, and evaluators.

References:

NWCG Equipment Time Recorder Position Page

NWCG Incident Position Standards for Equipment Time Recorder, PMS 350-51

NWCG Position Task Book for Equipment Time Recorder (EQTR), PMS 311-51

The Incident Position Standards and Next Generation Position Task Book are now available for Personnel Time Recorder (PTRC)

Date: November 13, 2024
Contact: Incident Business Committee

NWCG is excited to announce that the NWCG Incident Position Standards for Personnel Time Recorder, PMS 350-53 and NWCG Position Task Book for Personnel Time Recorder (PTRC), PMS 311-53 are now available.

The Performance Support Package, which for PTRC, includes the Incident Position Standards and Next Generation Position Task Book were developed through the Incident Performance and Training Modernization (IPTM) effort. The Performance Support Package will support trainees, those qualified in the position, and evaluators.

References:

NWCG Personnel Time Recorder Position Page

NWCG Incident Position Standards for Personnel Time Recorder, PMS 350-53

NWCG Position Task Book for Personnel Time Recorder (PTRC), PMS 311-53